News | April 28, 2016

MRI Inclined Plate Settlers Upgrade Richmond, VA Plant To 140 MGD

Untitled.jpg

Water treatment plant improvement project now in second phase

Meurer Research, Inc.’s patented Inclined Plate Settlers and Hoseless Cable-Vac Sludge Collectors are being installed to replace aging equipment, improve effluent quality and enhance solids removal at the Richmond, VA Water Treatment Plant. The MRI system is designed for a maximum peak flow of 140 million-gallons-per-day. 

To retrofit the four sedimentation basins, MRI equipment is being installed in one basin per year over a four-year period. The phased approach enables the city of Richmond plant – one of the largest water producers in Virginia – to be upgraded without interrupting operations. 

Retrofitting of the second basin will be completed this year.

MRI – an engineering and manufacturing company with over 50 patents and thousands of installations of advanced water and wastewater treatment equipment – designed and built the plate settlers and sludge collectors to meet site specifications of engineering firm, Whitman, Requardt & Associates, LLP. 

Situated along the James River, the 230-foot basins are slightly curved and longer than typical sedimentation basins. In addition, the basin depths are five feet shallower than normal and installation access is limited. The unique shape and installation challenge required a highly customized design. 

“We did all of the design work upfront in order to facilitate installation planning and budgeting. Discussions about upgrading the plant began five or six years ago and the equipment design was central to the project. We were glad to be instrumental in the planning,” said Joe Brauch of Meurer Research, Inc. 

Each of the basins is being retrofitted with 3,150 Inclined Plate Settlers and nine Hoseless Cable-Vac Sludge Collectors for a maximum peak flow of 35 MGD, or 140 MGD total for the four basins. 

“Normally, the sludge collector travels in the direction of the water flow. To accommodate the curvature and long length of the basin, we are running the sludge collectors across the width of the basin instead,” said Brauch. 

The layout enables plant operators to run the sludge collectors at the front end of the basin more often where heavier and more solids settle. 

MRI also provided the stainless steel walkways and effluent troughs for each basin. The new system is designed for future expansion with the capacity to treat an additional 12 MGD per basin. 

Installation in the first basin was completed in 2015. Preparation for installation in the second basin is underway with the full install slated to be completed this year. The final two basins will be completed in 2017 and 2018 respectively. 

About Meurer Research, Inc.
Meurer Research, Inc. engineers and manufactures advanced water and wastewater treatment products to solve the complex issues facing treatment facilities worldwide. Founded in 1978, MRI has over 50 patents and more than 5,000 installations cleaning more than 3 billion gallons of water each day. MRI recently installed its 1,000thHoseless Cable-Vac Sludge Collector. The company designs, manufactures, installs, and offers after-market customer service for a range of products including Inclined Plate Settlers, Hoseless Cable-Vac and Ultra-Scraper Sludge Collectors, Flocculation Systems, Pilot Systems, and Package Systems for Water and Wastewater. For more information, visit www.meurerresearch.com. 

Source: Meurer Research, Inc.